​​​​​20​   Sheffield / Waddington Water Supply


20.1       Scheme Summary


Description​ Quantity
Estimated Population Served ​
592

Scheme Coverage

(1 Jan 2021)

Full Charges156
Half Charges0
>1 Charges48 (46 restricted)
System Components ​​ ​​ ​​ ​
Bores/Intakes (No.)2
Treatment/DisinfectionUV
Reservoirs (No.)1
Pump Stations (No.)
0
Piped (m)40,607.95
HistoryOriginal scheme installation date1990
​Value ($) ​
Replacement Cost$4,384,297
Depreciated Replacement Cost$3,053,066
FinancialOperator cost (scheduled and reactive maintenance) per connection​
$370.78/connection

Demand (m3)

(1 Jan – 31 Dec 2020)​

Average daily310
Peak daily631
Minimum daily8.4
Average daily per connection1.47
Type of Supply 
High pressure with restricted and unrestricted
Target Pressure & Flow at boundary ​
Pressure>310kPa (150kPa restricted)
Flow>20L/min (±10% maric restricted)
SustainabilityWell SecurityUnsecure

 

20.2       Key Issues

Th​e following key issues are associated with the Sheffield/Waddington water supply.  A list of district wide issues are located in 5Waters Activity Management Plan: Volume 1.

​​Table 20‑1 Sheffield/Waddington Scheme Issues

What's the Problem​ What we plan to do
Required infrastructure upgrades include pump upgrades, mains duplication and treatment plant upgrades. Council confirm its renewal programme and align renewals with required upgrades to ensure efficiencies prior to undertaking the works. 

 

20.3       Overview & History

Sheffield/Waddington townships were the last major townships in the Malvern County Council to be reticulated. Previously household water was obtained by either the use of stock water races, shallow wells or rain water tanks that were subject to contamination.

Sheffield/Waddington water supply provides treated surface water from two shallow wells located in Hawkins River gravels (adjacent to Hawkins River) to properties located in both the Sheffield and Waddington townships.  The water is treated by UV disinfection.

The scheme was installed in 1990 as an unrestricted water supply with full “Fire Fighting Capacity" at the time.  Extensions to the scheme into the rural area occurred in 1994 and 1996.  These extensions were only for domestic use and are restricted to 2m3 per day. 

CPW shared water use agreement.

The Council's Long Term Plan 2015-2025 identifies one of the major projects to be the Council's commitment to 'work with Central Plains Water to develop a concept for converting the Kowai River sourced water race network (part of the Malvern Water Race Scheme) into a combined water race and irrigation network. This concept will then be used for further consultation with the community.​​

The Council entered into agreement with CPW on 16th December 2016.  The philosophy of the Agreement is to achieve a mutually beneficial cost neutral position.  While the Scheme will benefit from a potential 200l/s of reliable water for irrigation, the added value the Scheme will provide to the community includes providing a robust and secure long term piped water supply to both the Sheffield and Springfield drinking water treatment stations.  Which, from a water quality perspective enables the Council to avoid use of shallow groundwater during periods of high turbidity in adjoining rivers, or as required for capacity augmentation; and providing the necessary water quantity to support future township expansion.  In addition, a piped stock water supply to shareholders and non-shareholders will ensure this historical network is upgraded to a high quality, efficient utility.

​​​
​​ Figure 20-1
SHEFFIELD WADDINGTON Water - Scheme map

Open larger map: 'Water Scheme'

V2 Sheffield - Scheme Schematic.png

Figure 20‑2 Scheme Schematic


20.4       System Capacity

This water supply was designed as an unrestricted supply but later extensions into the rural area were provided for domestic use and are restricted to 2m3/day. 

Table 20‑2 Capacity Summary

 ​

Flow Rate (L/s)

Daily Volume (m3)

Annual Volume (m3)

Comments
Abstraction Capacity12.51080-Two bore pumps
Treatment Capacity>= abstraction--UV due for renewal
Consented Take11.71010245,430CRC173786 **
Peak Demand15 (typical)726 *118,000 

 * 1 March 2015 ​ ** Consent allows water to be shared as part of a water users group.  Refer CRC173786 & CRC173785​ ​ 


20.5       Resource Consents

The Sheffield/Waddington water supply has a number of resource consents. Table 20‑3 shows the water take permitted by the resource consents for this scheme.

Table 20‑3 Resource Consents

Consent

 ​

Description​ Location Date Issued Expiry Date Consented Max Instantaneous Flow (L/s) Consented Max Daily Volume (m3/day)

CRC173786

To take and use groundwaterRoecombe Road, SHEFFIELD7-Feb-174-May-3611.71010

 

20.6       Water Quality

The Sheffield/Waddington supply is a non-secure source which is currently sampled twice weekly at the source, treatment plant and weekly in the reticulation zone.

The following details E. coli transgressions for the period 2012 to 2020.


Source

There have been 117 incidences of E. coli identified in source water samples during this period, highlighting the importance of water treatment for this scheme.

​​​Figure 20‑3 E. coli Transgressions - Source


Treatment

There have been two E. coli treatment transgressions during this period; in August 2012 and March 2020.

Zone

There have been five E. coli Zone transgressions during this period.​

Figure 20‑4 E. coli transgression – Reticulation Zone


Chemical Analysis

The following is a summary of the raw water chemical analysis carried out at the Sheffield/Waddington Water Supply. 

Table 20‑4 Sheffield/Waddington Water Supply Raw Water Chemical Analysis Summary

Parameter

Standards
20152017 Status
Total Lead (g/m3)0.01 (Maximum Acceptable Value)
0.000250.001670
pH (pH units)7-8.5 (Guideline Value)
7.27.0
Total Hardness (g/m3 as CaCO3)<200 (Guideline Value)
5245.2
Total Calcium (g/m3)n/v13.111.70
Total Iron  (g/m3)<0.2 (Guideline Value)
<0.021< 0.021
Total Sodium (g/m3)<200 (Guideline Value)
8.77.89
Nitrate - Nitrogen (g/m3)11.3 (Maximum Acceptable Value)
32.9


20.7       Scheme Assets

A summary of material and diameter for pipes in Sheffield/Waddington is shown below in Figure 20‑5 and Figure 20‑6.

Figure 20‑5 Pipe Material – Sheffield/Waddington


Figure 20‑6 Pipe Diameter – Sheffield/Waddington

 

20.8       Operational Management

The water supply is operated and maintained under two maintenance contracts as follows:

  • Contract 1241: Water Services Contract.  Contract is with SICON who undertakes investigations, conditions inspections, proactive and reactive maintenance and minor asset renewals; and
  • Contract 1202: Parks and Reserves Contract.  Contract is with SICON who undertakes the maintenance of land scape features related to water services e.g. mowing, gardens etc.

Water quality sampling is completed under an agreement with Food and Health Ltd as required.

 

20.9       Photos of Main Assets


​​Sheffield - Photo 1 Well No. 2.jpg
Photo 1: Well No. 2 (typical of both wells) with Reservoir on hill in background (Well No. 1 further along road)






​​V2 Sheffield - Photo 2 Treatment Shed.jpeg

Photo 2: Treatment Shed

 

20.10       Risk Assessment

A risk assessment has been undertaken for the Sheffield/Waddington scheme. The key output from the risk assessment is the identification of any extreme and high risks which need to be mitigated. In order to mitigate these risks they have been included and budgeted for in the projects within this LTP. Table 20‑5 outlines the risk priority rating, Table 20‑6 outlines the risks and the list of key projects is found in Table 20‑11.

Table 20‑5 Risk Priority Rating

Risk Score​ Level of Risk Risk Response
> 50Extreme

Awareness of the event to be reported to Council. 

Urgent action to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

35-50Very HighRisk to be eliminated / mitigated / managed through normal business planning processes with responsibility assigned.
14-35HighManage risk using routine procedures.
3.5-14ModerateMonitor the risk.
< 3.5Low

Awareness of the event to be reported to Council. 

Immediate action required to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.


Table 20‑6 Risks – Sheffield/Waddington

Risk​ Action/Project Year Identified 2014 Risk Rating 2017 Risk Rating Residual Risk Rating
Inability to flush wellsInstall flushing points on wells20142777
Inadequate treatmentDesign new treatment system UV and Filtration20144077
Inadequate treatmentInstall filtration2014404040
Electrical failure due to lightning or network spikesInstall surge diverters2014101010
Failure to meet NES water meter standardsNES Water Meter Compliance20142066
Inability to collect income from non-metered propertiesInstall property water meters201427272.1
Non-consented activitiesRenewal of consents201427276
Bore head risksraise above ground and backflow2017 101
inadequate chlorine residence time direct pipe to res2017 270.7


The list of district wide risks can be found in 5Waters Activity Management Plan: Volume 1.


20.11      Asset Valuation Details

The total replacement value of assets within the Sheffield/Waddington water scheme is $4,384,297 with further details in Table 20‑7 below.

Table 20‑7 Replacement Value, Sheffield/Waddington

Asset Class 1​ Asset Class 2 Sum of Replacement Value
Plant and Equipment ​$688,459
Water Reticulation ​​ ​​ ​​ ​
Hydrant
$34,083
Lateral$98,404
Pipe$3,335,432
Supply Point$187,692
Valve$40,227


20.12       Renewals

The renewal profile has been taken from the 2019 5 Waters Valuation. A graph showing the renewals for this scheme are shown by Figure 20‑7 below. There is a backlog of renewals that are overdue. Future renewals are relatively evenly spread across years.

Figure 20‑7 Sheffield/Waddington Water Renewal Profile

 

20.13       Critical Assets

The criticality model for Sheffield/Waddington has been updated for the 2021 AcMP. The methodology of the criticality model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the criticality has been calculated for the reticulation assets. Table 20‑8 and Figure 20‑8 below shows the calculated criticality for all of the assets within this scheme that have a recorded known length.

Table 20‑8 Length of Assets per Criticality Level

Criticality Bands​ Length (m)
5
Low33,925
4
Medium-Low4,057
3
Medium2,461
2
Medium-High2,614
1
High0​


​​​
​​ Figure 20-8
SHEFFIELD WADDINGTON Water - Criticality map

Open larger map: 'Water Criticality'


20.14       Asset Condition

The asset condition model was run for Sheffield/Waddington in 2021. The methodology of the model can be found in 5Waters Activity Management Plan: Volume 1 which provides details of how the model has been calculated for the pipe reticulation assets. Figure 20‑9 below shows the level of asset condition for these assets within this scheme that have a recorded known condition.

​​​
​​ Figure 20-9
SHEFFIELD WADDINGTON Water - Condition map

Open larger map: 'Water Condition'

Table 20‑9 provides a description of the condition rating used within the condition model.

Table 20‑9 Asset Condition Grading

Condition Rating​ Grading
1.0Excellent
2.0Good
3.0Moderate
4.0Poor
5.0+Fail

 

The number of pipe faults is also measured through the asset management system. Figure 20‑10 shows the known historic pipe failures within this scheme.

​​​
​​ Figure 20-10
SHEFFIELD WADDINGTON Water - Pipe Faults map

Open larger map: 'Water Pipe Faults'

​20.15       Funding Program

The 10 year budgets are shown by Table 20-10​. Bu​dgets are split into expenditure, renewals, projects and capital projects. Expenditure and renewals have been reported on a district-wide basis in Volume 1. 

All figures are ($) not adjusted for CPI “inflation".  They are calculated on historical data, and population growth where relevant.​

Table 20-10 Budget Summary

Years Projects Capital Projects
2021/2022 -
 $70,000
2022/2023
 -
 $50,000
2023/2024 -
 $400,000
2024/2025 -
 -
2025/2026 -
 -
2026/2027 -
 -
2027/2028 -
2028/2029
 -
 -
2029/2030
 -
 $400,000
2031/2032
 -
 -
Total -
 $920,000

An explanation of the categories within the budgets are as follows below:

  • Expenditure consists of operation and maintenance costs;
  • Renewals are replacement of assets which are nearing or exceeded their useful life;
  • Projects are investigations, decisions and planning activities which exclude capital works; and
  • Capital projects are activities involving physical works.

Table 20-11 Key Projects

Account Label​ GL Description​  Year 1($)  Year 2($)  Year 3($) Years 4 to 10 Funding Split *
​Capital Projects​
-
Second pipe to reservoir
 -
-
$400,000
-
TBC
​Capital Projects
​-
​Second reservoir or VSD
​$40,000
​-
-
​$400,000
​TBC

​Capital Projects
-
Post-UV/filter flushing
​$30,000
-
​-
​-
100% LoS
​Capital Projects
​-
​Additional monitoring sites
​-
​$50,000
​100% LoS

 * Where LoS refers to Level of Service and G refers to Growth

The list of district wide projects can be found in 5Waters Activity Management Plan: Volume 1.

Discussion on Projects

Projects​​​ have been determined based on their:

  • Relevance to the scheme
  • Requirement to be completed under legislation
  • Ability to bring the scheme up to or maintain the Level of Service required under council's Asset Management Policy. 

Many projects are jointly funded by more than one scheme and activity.  Each scheme pays a pro-rata share only, equivalent to the number of connections.

Discussion on Capital and Projects

Where relevant, Capital (Levels of Service) and Capital (Growth) projects have been included in the scheme financial details. 

Levels of Service Projects and growth splits have been provided to ensure the costs of population driven works are clear.​​​​​