​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​<< ​​5-Waters-Volume-3-Wastewater
​​​​​​​​​​​​​​​​​​<< ​​Leeston Wastewater Scheme​​​
Prebbleton Wastewater Scheme​​ >>​​​

​​​​​​​​​​​​10   Lincoln Wastewater Scheme


10.1       Scheme Summary

 

Description Quantity
Estimated Population Served ​
8,373

Scheme Coverage

(1 Jan 2021)

​​ ​
Full Charges2,520
Half Charges322
>1 Charges44
System  Components ​​ ​​ ​​ ​
Piped (m)113,340
Manholes (No.)947
Pump Stations (No.)14
TreatmentN/A (to Pines WWTP)
DisposalN/A (to Pines WWTP)
HistoryOriginal scheme installation date1964
Value ($) ​
Replacement Cost$56,108,676
Depreciated Replacement Cost$45,989,974
Financial
Operator cost (scheduled and reactive maintenance) per connection

$80.65/connection

Demand ​​ ​​ ​​ ​
(1 Jan - 31 Dec 2020)​
Annually (m3) 711,328
Average daily (m3) 1,949
Peak daily (m3) 3,667
Minimum daily (m3) 38
Infiltration Yes
SustainabilityUltimate discharge pointTo Pines WWTP Land Disposal

 

10.2       Key Issues

The following key issues are associated with the Lincoln Wastewater Scheme.  A list of district wide issues are located in 5Waters Activity Management Plan: Volume 1.

Table 101 Lincoln Scheme Issues

What's the Problem​ What we plan to do
Significant infiltration and inflow is experienced during wet weatherTarget renewals to address infiltration and investigate sources of infiltration
Meeting growth demandsCapital upgrades as required to meet growth demands

 

10.3       Overview & History

In 1986 an oxidation pond with discharge to the LII River was installed with subsequent closure of the previously used Pasveer treatment plant. (Marion Place)

In early 1991 a Council Project Team recommended and received approval for the installation of aeration tanks that could be converted to a Sequential Batch Reactor (SBR) system.  Three aeration tanks were installed and commissioned in 1993 but SBR's were not installed

A Council led Project Team was set up in the mid 1990's to consider the options for wastewater treatment and disposal as the consent for discharge to the Lll was due to expire. 

An agreement between Selwyn District Council and Christchurch City Council was signed in November 1997 allowing pumping of treated wastewater from Lincoln Sewage Treatment Plant to Christchurch City's sewerage scheme.  The permitted period of pumping was from 6pm to 4am at a maximum flow rate of 50L/sec.  The maximum volume of discharge was 1,200,000m3 in each financial year. In 1998 construction of the pump station and rising main from Lincoln through to Christchurch city sewer reticulation was completed.

The growth of Prebbleton and Lincoln was limited by the discharge restrictions as defined in the CCC agreement.  Without an alternative solution being adopted, no further growth could occur.  Similarly for Rolleston, there would be limited growth without greater capacity of treatment and conveyance being constructed in accordance with the master plan, even on a standalone basis.  Council therefore decided to investigate the options available for servicing the wider community to meet current and future needs, and subsequently formed the basis for the establishment of the Eastern Selwyn Sewerage Scheme.

From December 2012 Lincoln township wastewater treatment and disposal has been undertaken at the Pines WWTP (Rolleston) as part of the Eastern Selwyn Sewerage Scheme (refer Section 5.0). The Lincoln oxidation pond is now only used as a contingency measure in emergency situations for buffer storage.

2010/2011 Earthquakes

The 2010/2011 earthquakes had a minor impact on the scheme's below ground infrastructure.  Several deep lateral connections separated but were repaired.  Based on visual assessment (CCTV and qualified staff) no other damage to the below ground infrastructure or resulting effects e.g. blockages have been detected.  There may however be long term but intangible impacts on maintenance and renewals programmes.

​​​
​​ Figure 10-1
LINCOLN Sewer - Scheme map

Open larger map: 'Sewer Scheme'

V3 Lincoln - Scheme Schematic 1 of 3.png

V3 Lincoln - Scheme Schematic 2 of 3.png

V3 Lincoln - Scheme Schematic 3 of 3.png

Figure 10‑2 Scheme Schematic x3


V3 Lincoln - Master Plan.png

Figure 10‑3 Lincoln Master Plan


 V3 Lincoln - Pump Station Failure Map.jpg

Figure 104 Pump Station Failure Map

 

10.4       System Capacity

In recent years there has been rapid residential growth in the Lincoln community. This has placed a strain on the existing wastewater collection system. Therefore, with the implementation of the ESSS, the wastewater system has been expanded in stages to meet the increasing flows. A wastewater masterplan has been established to structure the expansion of scheme to meet the timing of new development.  The capacity of existing catchment pump stations, while not yet reached, will need to be monitored and upgraded as pump renewals are considered.

Figure 10‑5 below outlines the projected population growth within Lincoln.

V3 Lincoln - Projected PE growth.png 

Figure 105 Projected PE growth – Lincoln

 

Emergency Storage

The oxidation pond operates at a normal operating volume of 55,000m3 (7.0m).  It can be raised to 7.6m or an additional 20,400m3.  This would allow for 5-7 wet weather days storage from Lincoln before discharge would have to occur.

V3 Lincoln - Wet Weather Flow Capacity Map.jpg

Figure 106 Wet Weather Flow Capacity Map

 

10.5       Resource Consents

The Lincoln wastewater scheme is part of the ESSS scheme. Therefore, all wastewater is pumped to the Pines Treatment Plant located in Rolleston. The resource consents required for this treatment plant are in the ESSS section of this plan. There is a single resource consent for Lincoln, as shown in Table 10‑2.

Table 102 Resource Consents

Consent​​

Description Location Date Issued Expiry Date

CRC145804


To discharge to air from a sewage air valve21 Allendale Lane, Lincoln8-Apr- 14 N/A

 

10.6       Scheme Assets

A summary of the assets within this scheme is outlined in this section.


10.6.1   Reticulation Overview

A summary of material and diameter for pipes is shown in Figure 10‑7 and Figure 10‑8.

Figure 107 Pipe Material - Lincoln


Figure 108 Pipe Diameter – Lincoln

 

10.6.2   Treatment and Disposal

Council has installed a bulk wastewater conveyance pipeline from Lincoln to the Rolleston Pines site via the Selwyn Road Pump Station (completed February 2012).  This allows Prebbleton, Springston and Lincoln's sewage to be pumped to the Rolleston Pines site for treatment and disposal.

No decision has been made on relinquishing the discharge right accorded under the agreement between CCC and SDC.

Table 103 Treatment and disposal facilities

System Description Year Installed/ Upgraded

Aeration Tanks

(Emergency Storage)

Three aeration tanks with aerators

Now used for online, peak flow lopping being directly connected to the Allendale Lane PS

1991

Oxidation Pond

(Emergency Storage)

Single stage pond of 3.2ha

Acts as a storage buffer when inflows exceed Pines treatment capacity

1986

Pump Station to CCC system

(Life line)

For disposal of treated wastewater via

DN250 pipeline to CCC system at Hornby.

Maximum permitted discharge is 50 L/s during a daily 10 hour period between 6 pm and 4 am.

The wastewater discharge standard is 50g/m3 BOD and 50g/m3 suspended solids.

1998


Further reference to the treatment and disposal of Lincoln wa​​stewater is described in Eastern Selwyn Sewerage Scheme​.

 

10.6.3   Design

The wastewater collection system has been designed in accordance with the appropriate New Zealand engineering design guidelines at the time of construction and in accordance with the Selwyn District Council Engineering Design Standards. Specific designs for portions of the scheme outside of these standards have been considered where detailed engineering designs have been provided.


10.6.4    Pump Stations

There are currently a total of eleven pump stations, ten pump stations within the Lincoln reticulation and one pump station at the Lincoln treatment plant which has the ability to pump effluent to the Christchurch City reticulation.  Details are tabled below.

Pump stations where the standby / assist pump is predicted to start have been highlighted in yel​low and r​​​ed for those that experience a peak wet weather response.

Yellow    Pumps are can convey the peak flow without backing up the system

Red        Pumps are unable to convey the peak flow causing the system to back up

Table 104 Pump Station Overview

Site Name Wet well dimensions No of pumps Pump curve used Recorded instantaneous pump rate (L/s) Model Pump Rate (L/s) ADWF (L/s) PDWF (L/s) PWWF 1 in 5 year ARI (L/s)
Lincoln (S)
Edward St PS
1500Ø2Flygt 3127 181 MT43922191.53.8 23.1​​​
Lincoln (S)
Faulks Dr PS
2050Ø2Flygt 3171 181 SH27034310.20.59.3
Lincoln (S)
Liffey Springs PS
2050Ø2Flygt 3153 181 HT45042370.61.55.9
Lincoln (S)
Lincolndale PS
3500Ø2Flygt 3153 180 HT45042
423.713.2 49.5​
Lincoln (S)
LLD PS
2550Ø2Flygt 3202 180 HT45674779.319.8101.4​
Lincoln (S)
Millstream Dr PS
1800Ø2Flygt 3085 182 MT47012
110.20.40.4
Lincoln (S)
Roblyn Pl PS
1800Ø2Flygt 3102 180 MT433  0.10.42.9
Lincoln (S)
Ryelands PS
1800Ø2Flygt 3085 182 HT25288.71.53.3 12.1​

 

Table 105 Pump Station Storage Time Analysis

Pump Station   Hours until HLA reached Hours until first spill Spill Location -
AMS ID
Lincoln (S)
Edward St PS
Pumps into main catchment4.46.8550083
Lincoln (S)
Faulks Dr PS
Pumps directly to Allendale Lane145.1156.6622813
Lincoln (S)
Liffey Springs PS
Pumps directly to Allendale Lane52.259.3620237
Lincoln (S)
Lincolndale PS
Pumps directly to Allendale Lane6.99.6550863
Lincoln (S)
LLD PS
Pumps directly to Pines WWTP via Selwyn road3.24.2604033
Lincoln (S)
Millstream Dr PS
Pumps to Edward St25.930.5550406
Lincoln (S)
Roblyn Pl PS
Pumps into main catchment24.225.9550008
Lincoln (S)
Ryelands PS
Pumps directly to Allendale Lane14.720.7595957

The Hasendene (Murray Place) Pump Station, Barker St Pump Station, Marion Pl Pump Station have been decommissioned.

 

10.6.5   Rising Mains

Table 106 Rising Main Overview

Pump Station Town Total Length (m) Total Volume (m3) ADWF (L/s) Uphill Retention Time (hours) Drain Time (hours) Total Time (hours) Model Max Pressure (kPa) SCADA Max Pressure (kPa)
Lincoln (S)
Edward St PS
Lincoln3275.21.51.00.01.045No data
Lincoln (S)
Faulks Dr PS
Lincoln1,71439.60.252.80.0 52.8​
360No data
Lincoln (S)
Liffey Springs PS
Lincoln1,13432.00.615.20.015.2​
150170 - 250
Lincoln (S)
Lincolndale PS
Lincoln89334.63.72.60.02.6170130 - 210
Lincoln (S)
LLD PS​​​
Lincoln673
26.59.30.80.00.8170No data
Lincoln (S)
Millstream Dr PS
Lincoln1340.70.20.10.40.510No data
Lincoln (S)
Roblyn Pl PS
Lincoln320.30.10.50.00.530No data
Lincoln (S)
Ryelands PS
Lincoln4934.21.50.80.00.880No data

 

10.7       Operational Management

The wastewater schemes are operated and maintained under the maintenance contract as follows:

  • ​Contract 1241: Water Services Contract.  Contract is with SICON who undertakes investigations, conditions inspections, proactive and reactive maintenance and minor asset renewals.

Wastewater sampling is completed under an agreement with Food and Health Ltd as required.

 

10.8       Photos of Main Assets


V3 Lincoln - Photo 1 – Buffer storage tanks.jpg
Photo 1 – Buffer storage tanks
V3 Lincoln - Photo 2 – Pond for additional buffer storage.jpg
Photo 2 – Pond for additional buffer storage
V3 Lincoln - Photo 3 - Ryelands Pump Station.jpg
Photo 3 - Ryelands Pump Station 
V3 Lincoln - Photo 4 – LLD Pump Station.jpg
Photo 4 – LLD Pump Station


10.9       Risk Assessment

A risk assessment has been undertaken for the Lincoln scheme. The key output from the risk assessment is the identification of any extreme and high risks which need to be mitigated. In order to mitigate these risks they have been included and budgeted for in the projects within this LTP. Table 10‑7 details the risk priority rating, Table 10‑8 outlines the risks and the list of key projects is found in Table 10‑13.

Table 107 Risk Priority Rating

Risk Score​ Level of Risk Risk Response
> 50Extreme

Awareness of the event to be reported to Council. 

Urgent action to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

35-50Very HighRisk to be eliminated / mitigated / managed through normal business planning processes with responsibility assigned.
14-35HighManage risk using routine procedures.
3.5-14ModerateMonitor the risk.
< 3.5Low

Awareness of the event to be reported to Council. 

Immediate action required to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.


Table 108 Risks - Lincoln

Risk Action/Project Year Identified 2014 Risk Rating 2017 Risk Rating Residual Risk Rating
Aeration of pond is not sufficient resulting in odour generationinstall additional aerator2014272727
Infiltration could overwhelm sewer pump station and ESSS networkDesign high flow diversion to oxidation ponds including drawings and tender documents2014203.53.5
Infiltration could overwhelm sewer pump station and ESSS networkAllendale Lane Sewage Site - install an automate "valve" (between Allendale Lane pump station and tanks) and a larger pipe between storage tanks and pond.201410103.5
LLD sewer PS capacity is exceededDesign additional storage for LLD sewer pump station2014103.53.5
LLD sewer PS capacity is exceededUpgrade LLD pump station with additional storage2014103.53.5
Safe removal of pumpsAllendale gantrey 2017 456
Poor understanding of catchment flowsRoblen Pl - Flow meter2017 92
Scheme efficiency review storeage and pump operation 2017 126


The list of district wide risks can be found in 5Waters Activity Management Plan: Volume 1.

 

10.10       Asset Valuation Details

The total replacement value of assets within the Lincoln Scheme is $56,108,676 as detailed in Table 10‑9 below. 

Table 109 Replacement Value, Lincoln

Asset Class 1 Asset Class 2 Sum of Replacement Value
Plant and Equipment ​
$1,491,722
​Wastewater Reticulation ​​ ​​ ​​ ​
Chamber$294,392
Lateral$9,138,118
Manhole$4,991,806
Pipe$40,045,646
Valve$146,991


10.11       Renewals

The renewal profile has been taken from the 2019 5 Waters Valuation. A graph showing the renewals for this scheme are shown by Figure 10‑9 below.

Figure 109 Lincoln Wastewater Renewal Profile

 

10.12          Critical Assets

The criticality model for Lincoln has been updated for the 2021 AcMP. The methodology of the criticality model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the criticality has been calculated for the reticulation assets. Table 10‑10 and Figure 10‑10 below show the calculated criticality for all of the assets within this scheme that have a recorded known length.

Table 1010 Length of Assets per Criticality Level

Criticality Bands Length (m)
5
Low57,348
4
Medium-Low20,590
3
Medium18,612
2
Medium-High11,725
1
High2,068​

 

​​​
​​ Figure 10-10
LINCOLN Sewer - Criticality map

Open larger map: 'Sewer Criticality'

​​​

10.13       Asset Condition

The asset condition model was run for Lincoln in 2021. The methodology of the model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the model has been calculated for the reticulation assets (particularly pipes). Figure 10‑11​ below shows the level of asset condition for all of the assets within this scheme that have a recorded known condition.​

​​​
​​ Figure 10-11
LINCOLN Sewer - Condition map

Open larger map: 'Sewer Condition'

​Table 10‑11 provides a description of the condition rating used within the condition model.

Table 1011 Asset Condition Grading

Condition Rating​ Grading
1.0Excellent
2.0Good
3.0Moderate
4.0Poor
5.0+
Fail

 

10.14       Funding Program

The 10 year budgets for Lincoln are shown by Table 10‑12. Budgets are split into expenditure, renewals, projects and capital projects. Expenditure and renewals have been reported on a district-wide basis in Volume 1. 

All figures are ($) not adjusted for CPI “inflation".  They are calculated on historical data, and population growth where relevant.

Table 1012 Lincoln Budget Summary

Years​ Projects Capital Projects
2021/2022 -
-
2022/2023 -
$100,000
2023/2024 -
-
2024/2025 -
-
2025/2026 -
-
2026/2027 -
-
2027/2028
 -
-
​2028/2029
​-
​-
​2029/2030
​-
​-
​2030/2031
​-
​-
Total -
$100,000

 

An explanation of the categories within the budgets are as follows below:

  • Expenditure consists of operation and maintenance costs;
  • Renewals are replacement of assets which are nearing or exceeded their useful life;
  • Projects are investigations, decisions and planning activities which exclude capital works; and
  • Capital projects are activities involving physical works.

Table 1013 Key Projects

Account Label GL Description  Year 1 ($)  Year 2 ($)  Year 3 ($) Years 4 to 10 Funding 
Split *
Capital Projects-
Alterations to road layout for pump station
 -
 $100,000
 -
-
TBC

* LoS refers to Level of Service; G refers to Growth

​The list of district wide projects can be found in 5Waters Activity Management Plan: Volume 1.

Discussion on Projects

Projects have been determined based on their:

  • Relevance to the scheme
  • Requirement to be completed under legislation
  • Ability to bring the scheme up to or maintain the Level of Service required under council's Asset Management Policy. 

Many projects are jointly funded by more than one scheme and activity.  Each scheme pays a pro-rata share only, equivalent to the number of connections.

Discussion on Capital and Projects

Where relevant, Capital (Levels of Service) and Capital (Growth) projects have been included in the scheme financial details. 

Levels of Service Projects and growth splits have been provided to ensure the costs of population driven works are clear.

 

​​​​​​​​​​​​​​​​​​​<< ​​5-Waters-Volume-3-Wastewater
​​​​​​​​​​​​​​​​​​<< ​​Leeston Wastewater Scheme​​​
Prebbleton Wastewater Scheme​​ >>​​​

​ ​