​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​<< ​​5-Waters Volume 2 - Water Supplies
​​​​​​​​​​​​​​​​​​<< ​​Jowers Road Water Supply​​​
Lake Coleridge Water Supply​​ >>​​​

​12   Kirwee Water Supply


12.1       Scheme Summary


Description​ Quantity
Estimated Population Served ​
1,326

Scheme Coverage

(1 Jan 2021)

​​ ​
Full Charges357
Half Charges0
>1 Charges101
System Components ​​ ​​ ​​ ​
Bores/Intakes (No.)1
Treatment/DisinfectionUV Treatment
Reservoirs (No.)1
Pump Stations (No.)1
Piped (m)52,583
HistoryOriginal scheme installation date1981
Value ($) ​
Replacement Cost$5,920,750
Depreciated Replacement Cost$3,777,935
Financial
​Operator cost (scheduled and reactive maintenance) per connection
$155.96/connection

Demand (m3)

(1 Jan – 31 Dec 2020​)

​​ ​​ ​
Average daily606
Peak daily1,963
Minimum daily-
Average daily per connection1.2
Type of Supply Medium pressure restricted and unrestricted
Target Pressure & Flow at boundary ​
Pressure>310kPa (150kPa restricted)
Flow>20 L/min (±10% maric restricted)
SustainabilityWell SecuritySecure

 

12.2       Key Issues

The following key issues are associated with the Kirwee water supply.  A list of district wide issues are located in 5Waters Activity Management Plan: Volume 1.

​Table 12‑1 Kirwee Scheme Issues

What's the Problem​ What we plan to do
Due to the significant growth of Kirwee, new wells are required to meet demand.Council will continue to review the water infrastructure plan on an annual basis while considering actual and predicted growth.  Infrastructure will be provided as and when required in consideration of the urban/industrial split.  Detailed network modelling supports the infrastructure plan.

​Catchment management

​To encompass a holistic view of the drinking water supply improved liaison with ECan and study of ground water quality within the water supply protection zones are being investigated.

​Backflow risk

To prevent water supplies from the risk of backflow there is currently a district wide backflow prevention project underway. The Kirwee backflow project would focus on providing backflow prevention for all high risk users, rural connections and preventing backflow from the rural to urban sections of the water scheme.

​System redundancy

​System redundancy is highlighted as a key operational vulnerability due to the singular water source and treatment plant. To reduce this risk a second bore has been established with plan for connection to Kirwee water network.

 

12.3       Overview & History

The Kirwee water supply scheme is a high pressure metered on-demand (urban) and restricted (rural) scheme.   

The water supply was installed in 1981 to replace individual supplies from roof tanks and water races.  The township area was designed as a medium pressure, unrestricted supply, with restricted connections in the rural area for domestic use only (2m3/day per connection).  The township zone scheme has full “Fire Fighting Capacity".

The pumping and control system was upgraded in 1997 with additional pumps installed in both 2005/06 and 2009/10.

During the 2015-28 LTP period UV treatment and a backup generator was added to the scheme.

​​​
​​ Figure 12-1
KIRWEE Water - Scheme map

Open larger map: 'Water Scheme'

Kirwee - Scheme Schematic.png

Figure 12‑2 Scheme Schematic


12.4       System Capacity

Kirwee has potential for growth in terms of zoned land availability and projections suggest growth over the next 30 years.  The Kirwee supply also delivers a restricted supply to a small proportion (<10%) of properties.  On-demand (town) connections typically use less water but generate a higher peak flow rate, while restricted (rural) connections require more water but this is trickle fed at a low flow rate.  The restricted connections are not metered separately so this capacity assessment considers the supply as a whole.

Figure 12‑3 shows the projected growth in water demand for Kirwee in accordance with the latest house projections.

V3 Kirwee - Water Balance Assessment.PNG

Figure 12‑3 Kirwee Water Demand

The water take consent limits the maximum rate of take to 45 L/s.  This is greater than the installed pump capacity.  There is 450 m3 of reservoir storage and a booster pumping system so the maximum flow rate that can be supplied to the community is 53 L/s. The water take consent limits the maximum daily take to 3110 m3 (21,770 in any 7 day period).  The water supply is currently operating at its limit in terms of peak day demand and it is probable that water restrictions will need to be imposed from time to time to keep demand within the capacity of the infrastructure and the consented daily abstraction limit.  Peak summer demands are very high relative to average winter demand (8x greater), suggesting considerable scope for demand management.  Growth related infrastructure upgrades will be required. Council is trialling demand management measures which include reduced pressure management (reduced pressure 590KPA to 420KPA) and low level water restrictions. These issues may be resolved when the new source well comes online.

Table 12‑2 Existing Water Supply Capacity

 ​

Flow Rate (L/s)

Daily Volume (m3)

Annual Volume (m3)

Comments
Consented Take453,110***
396,450CRC158020
Peak Demand - current
38L/s2,400 *
245,000 **
 -
Abstraction capacity
363,110-

One bore pump

Capacity limited by consent

Distribution pumping
53.2
--
4 pumps (duty/assist) from 450m3 storage – can buffer peak flows but not peak days

* 15 January 2013, ** July 2012-June 2013, ​*** 21,770 per 7 days

Hydraulic models have been used to plan future water infrastructure for Kirwee, as part of a master planning exercise. The master planning provides an assessment of the sizing and timing of new infrastructure for new water sources (wells) and pipelines to service growth.  Part of the master planning requires a water balance to be developed to forecast growth, using historical peak demand per household.  The water balance forecasts the peak instantaneous flow per year versus the water resources available to determine the staging of new wells.  The well staging assumes that one well is redundant for each water supply, to take into consideration maintenance of wells, planning/timing of new wells and security of supply i.e. to maintain average/peak demand.  

The existing High Street well was modelled with a capacity of 36 L/s. The master planning exercise has identified that two new wells be required in Kirwee: one of which is near commissioining, and one which is required in 2022/23 to service growth (Table 12-4).​

Table 12‑3 Water Source Current Capacity

Sites Available​ Well Capacity (L/s)
High Street136

 

Table 12‑4 Water Source Future Capacity

New Site ID​ Location​ Planning Year Yield (L/s)
Kirw1
New Site (nr. Kirwee Model School)2021/22
35
​Additional
TBC​​2022/23
​30


Kirwee - Master Plan.png

Figure 12‑4 Kirwee Master Plan


12.5       Resource Consents

The Kirwee water supply has a number of resource consents. Table 12‑5 shows the water take permitted by the resource consents for this scheme.

Table 12‑5 Resource Consents

Consent​

 

Description Location Date Issued Expiry Date Consented Max Instantaneous Flow (L/s) Consented Max Daily Volume (m3/day)
CRC158020 To take and use groundwater.Hoskyns Road, KIRWEE DOMAIN11-Sep-0131-Jan-3545

3110

(21,770 per 7 days)

 

12.6          Water Quality

The Kirwee water supply is a secure source and is currently sampled twice weekly at the treatment plant and weekly in the reticulation zone. The following details E. coli transgressions for the period 2012 to 2020. 

Treatment

There have been two E. coli Treatment transgressions during this period which occurred in September 2013 and June 2017.

Zone

There have been 6 E. coli treatment transgressions during this period (excluding re-samples). Most of these transgressions have been attributed to the reservoir which has been upgraded.

Chemical Analysis

The following is a summary of the raw water chemical analysis carried out at the Kirwee Water Supply. 

Table 12‑6 Kirwee Water Supply Raw Water Chemical Analysis Summary

​​Parameter

Standards 
2008
​2011
​2013
201520172018
​2019
2020
Status
Total Lead (g/m3)0.01 (Maximum Acceptable Value)
​0.00011
​0.00034
​0.00025
<0.00011

0.000114​0.00011
​0.000194
​0.000139

pH (pH units)
7-8.5 (Guideline Value)
​-
​-
​-
7.87.7​-
​7.7
​7.8

Total Hardness (g/m3 as CaCO3)<200 (Guideline Value)
​45
​49
​52
54
49.3
​50.5
​51.4
​51.3

Total Calcium (g/m3)n/v​16
​16.6
​17.7
18.6
16.98​17.41
​17.71
​17.58
Total Iron  (g/m3)<0.2 (Guideline Value)
​0.05
<​0.021
​<0.021
<0.021< 0.021​< 0.021
​< 0.021
​< 0.021
Total Sodium (g/m3)<200 (Guideline Value)
​7.3
​7.7
7.9​8.4
7.94
​8
​8.38
​7.72
Nitrate - Nitrogen (g/m3)11.3 (Maximum Acceptable Value)
​3.6
​3.9
​4.4
4.8
4.32​3.99
​4.37
​4.91

12.7          Scheme Assets

A summary of material and diameter for pipes in Kirwee is shown in Figure 12‑5 and Figure 12‑6.

​Figure 12‑5 Pipe Material – Kirwee


​Figure 12‑6 Pipe Diameter – Kirwee

 

12.8       Operational Management

The water supply is operated and maintained under two maintenance contracts as follows:

  • Contract 1241: Water Services Contract.  Contract is with SICON who undertakes investigations, conditions inspections, proactive and reactive maintenance and minor asset renewals; and
  • Contract 1202: Parks and Reserves Contract.  Contract is with SICON who undertakes the maintenance of land scape features related to water services e.g. mowing, gardens etc.

Water quality sampling is completed under an agreement with Food and Health Ltd as required.


12.9       Photos of Main Assets


Kirwee - Photo 1 Well head.jpg
Photo 1: Well head
Kirwee - Photo 2 Reservoir and Pump Shed.jpg
Photo 2: Reservoir and Pump Shed


12.10       Risk Assessment

A risk assessment has been undertaken for the Kirwee scheme. The key output from the risk assessment is the identification of any extreme and high risks which need to be mitigated. In order to mitigate these risks they have been included and budgeted for in the projects within this LTP. Table 12‑7 outlines the risk priority rating, Table 12‑8 outlines the risks and the list of key projects is found in Table 12‑13.

Table 12‑7 Risk Priority Rating

Risk Score​​ Level of Risk Risk Response
> 50Extreme

Awareness of the event to be reported to Council. 

Urgent action to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

35-50Very HighRisk to be eliminated / mitigated / managed through normal business planning processes with responsibility assigned.
14-35HighManage risk using routine procedures.
3.5-14ModerateMonitor the risk.
< 3.5Low

Awareness of the event to be reported to Council. 

Immediate action required to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.


Table 12‑8 Risks – Kirwee

Risk​​​ Action/Project Year Identified 2014 Risk Rating 2017 Risk Rating Residual Risk Rating
Single source of supply - risk of supply interruptionCommission and connect abandoned Darfield well or add alternative source.2014404020
Electrical failure due to lightning or network spikesInstall surge diverters20142077
Failure to meet NES water meter standardsNES Water Meter Compliance20142066
Inability to collect income from non-metered propertiesInstall property water meters2014270.60.6
Non-compliance with the DWSNZDWSNZ - Age Testing2014200.70.7
Non-compliance with the DWSNZDWSNZ - Bore-head security2014202020
Non-consented activitiesRenewal of consents201427276
Backflow at treatment buildingInstall backflow2017 102
Ground chamber floodingNew soakhole to drain chamber2017 207

The list of district wide risks can be found in 5Waters Activity Management Plan: Volume 1.


12.11       Asset Valuation Details

The total replacement value of assets within the Kirwee water scheme is $5,920,750 with further details in Table 12‑9 below.

Table 12‑9 Replacement Value, Kirwee

Asset Class 1​ Asset Class 2 Sum of Replacement Value
Plant and Equipment ​
$1,099,287
Water Reticulation ​​ ​​ ​​ ​
Hydrant$171,742
Lateral$276,878
Pipe$3,854,378
Supply Point$397,034
Valve$121,431


12.12       Renewals

The renewal profile has been taken from the 2019 5 Waters Valuation. A graph showing the renewals for this scheme are shown by Figure 12​‑7 below. There is a backlog of assets due for renewal, and another peak in renewals in 2029/30​.

​Figure 12‑7 Kirwee Water Renewal Profile


12.13       Critical Assets

The criticality model for Kirwee has been updated for the 2021 AcMP. The methodology of the criticality model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the criticality has been calculated for the reticulation assets. Table 12‑10 and Figure 12‑8 below shows the calculated criticality for all of the assets within this scheme that have a recorded known length.

Table 12‑10 Length of Assets per Criticality Level

Criticality Bands​ Length (m)
5
Low38,563
4
Medium-Low4,391
3
Medium5,737
2
Medium-High520
1
High269​


​​​
​​ Figure 12-8
KIRWEE Water - Criticality map

Open larger map: 'Water Criticality'


12.14       Asset Condition

The asset condition model was run for Kirwee in 2021. The methodology of the model can be found in 5Waters Activity Management Plan: Volume 1 which provides details of how the model has been calculated for the pipe reticulation assets. Figure 12‑9 below shows the level of asset condition for these assets within this scheme that have a recorded known condition.

​​​
​​ Figure 12-9
KIRWEE Water - Condition map

Open larger map: 'Water Condition'

Table 12‑11 provides a description of the condition rating used within the condition model.

Table 12‑11 Asset Condition Grading

Condition Rating​​ Grading
1.0Excellent
2.0Good
3.0Moderate
4.0Poor
5.0+Fail

 

The number of pipe faults is also measured through the asset management system. Figure 12‑10​​ shows the known historic pipe failures within this scheme.

​​​
​​ Figure 12-10
KIRWEE Water - Pipe Faults map

Open larger map: 'Water Pipe Faults'

​ 

12.15       Funding Program

The 10 year budgets are shown by Table 12‑12. Bu​dgets are split into expenditure, renewals, projects and capital projects. Expenditure and renewals have been reported on a district-wide basis in Volume 1. 

All figures are ($) not adjusted for CPI “inflation".  They are calculated on historical data, and population growth where relevant.​

Table 12‑12 Budget Summary

Years​ProjectsCapital Projects
2021/2022 $26,000
 $50,000
2022/2023
 -
 $100,000
2023/2024 -
 $100,000
2024/2025 $5,000
 $400,000
2025/2026 -
 $50,000
2026/2027 -
 -
2027/2028 -
2028/2029
 -
 -
2029/2030
 -
 -
2031/2032
 -
 -
Total $31,000
 $700,000

An explanation of the categories within the budgets are as follows below:

  • Expenditure consists of operation and maintenance costs;
  • Renewals are replacement of assets which are nearing or exceeded their useful life;
  • Projects are investigations, decisions and planning activities which exclude capital works; and
  • Capital projects are activities involving physical works.

Table 12​‑13 Key Projects

Account LabelGLDescription​ Year 1($) Year 2($) Year 3($)Years 4 to 10Funding Split *
​Capital Projects​
-
New ringmain and/or parallel water main
 -
-
-
$400,000
TBC
​Capital Projects
​-
​Courtenay Road between Hoskins Road and Dawn Place: new connections
​-
​-
$100,000
​-

​TBC

​Capital Projects
​-
​Additional crossing of SH and rail; emergency line from Darfield
​-
​-
​-
​$50,000
​TBC
​Capital Projects
-
Pressure sensors added to network
​$50,000
-
​-
-
TBC
​Capital Projects
​-
​Backflow prevention devices
​-
​$100,000
​-
​-
​TBC
​Projects
​-
​Investigate options to improve system resilience/redundancy; investigate water loss; etc.
​$26,000
​-
​-
​$5,000
​TBC

 * Where LoS refers to Level of Service and G refers to Growth

The list of district wide projects can be found in 5Waters Activity Management Plan: Volume 1.

Discussion on Projects

Projects​​​ have been determined based on their:

  • Relevance to the scheme
  • Requirement to be completed under legislation
  • Ability to bring the scheme up to or maintain the Level of Service required under council's Asset Management Policy. 

Many projects are jointly funded by more than one scheme and activity.  Each scheme pays a pro-rata share only, equivalent to the number of connections.

Discussion on Capital and Projects

Where relevant, Capital (Levels of Service) and Capital (Growth) projects have been included in the scheme financial details. 

Levels of Service Projects and growth splits have been provided to ensure the costs of population driven works are clear.​​​​


​​​​​​​​​​​​​​​​​​<< ​​5-Waters Volume 2 - Water Supplies
​​​​​​​​​​​​​​​​​​<< ​​Jowers Road Water Supply​​​
Lake Coleridge Water Supply​​ >>​​​