​​​​​​​​​​​​​​​​​​<< ​​5-Waters Volume 2 - Water Supplies
​​​​​​​​​​​​​​​​​​<< ​​Darfield Water Supply​​​​​
Greater West Melton Water Supply​​​​​​​ >>​​​

​​​​​​​​​7   Dunsandel Water Supply


7.1       Scheme Summary

 

Description​​
Quantity
Estimated Population Served ​ 511

Scheme Coverage

(1 Jan 2021)

Full Charges 172
Half Charges 0
>1 Charges 4
System Components ​​ ​​ ​​ ​
Bores/Intakes (No.) 1
Treatment/Disinfection UV
Reservoirs (No.) 1
Pump Stations (No.) 1
Piped (m) 9,762
HistoryOriginal scheme installation date1986
Value ($) ​
Replacement Cost$1,906,696
Depreciated Replacement Cost$1,201,694
Financial

Operator cost (scheduled and reactive maintenance) per connection

$319.06/connection

Demand (m3)

(1 Jan – 31 Dec 2020)

​​ ​​ ​
Average daily336
Peak daily856
Minimum daily5.9
Average daily per connection1.78
Type of Supply 
Medium pressure and unrestricted
Target Pressure & Flow at bo​undary ​
Pressure>310 kPa
Flow>40 L/min
SustainabilityWell SecurityUnsecure

 

7.2          Key Issues

​The following key issues are associated with the Dunsandel water supply.  A list of district wide issues are located in 5Waters Activity Management Plan: Volume 1.

Table 71 Dunsandel Scheme Issues

What's the Problem What we plan to do
Supply is reliant on one source of water
Investigate an alternative site for a new bore.

​Catchment management

​To encompass a holistic view of the drinking water supply improved liaison with ECan and study of groundwater quality within the water supply protection zones are being investigated.​

​Backflow risk: the scheme is vulnerable to potential backflow issues associated with commercial and industrial connections. ​

There is currently a district wide backflow prevention project underway.

 

7.3       Overview & History

The Dunsandel Water Supply provides untreated groundwater to Dunsandel township and the adjacent 40 lot rural residential subdivision on Irvines Road (Sherwood Estate). 

The current scheme was formed by combining the Dunsandel Township (installed 1986) and Sherwood Rural Residential (installed in 1991) schemes in July 1997. This allowed decommissioning of the problematic Dunsandel Well (ECan number L36/0601), and an improved cost/benefit relationship for operating both schemes.

There was also a previous subdivision on the Hororata-Dunsandel Road constructed in 1976 with a communal water scheme that was absorbed and decommissioned with the Dunsandel Township work.

The scheme was designed as a medium pressure, unrestricted metered supply complying with NZ Fire Fighting Code of Practice. 

In 2009 the number of water quality transgressions rose significantly, and a combined regional, Selwyn District Council and community approach was taken to investigating the cause and recommending options to make the water safe to drink.  An ultraviolet light system was installed and has eliminated bacteria (E.coli) entering the township network.

​​​
​​ Figure 7-1
DUNSANDEL Water - Scheme map

Open larger map: 'Water Scheme'
Dunsandel - Scheme Schematic.png

Figure 72 Scheme Schematic

7.4       System Capacity

Dunsandel has some potential for growth in terms of zoned land availability.

Table 72 Capacity Summary

 

Flow Rate (L/s)

Daily Volume (m3)

Annual Volume (m3)

Comments
Consented Take251944291,600 (1)CRC010891.1
Peak Demand - current25L/s (2)1,380 (3)215,111 (4) 
Abstraction capacity24.72134-1 bore pump
Treatment capacity24.72134-Assume UV can accommodate bore pump flow rate.  Note current UV is non-compliant. And upgrade programmed 2015.
Distribution pumping
351944291,6002 pumps (duty/assist) from 70m3 storage – can buffer peak flows but not peak days

​(1) inferred value, (2) Jan 2013, (3) 25 Jan 2015 (excluding fire fighting events), (4) Dec 2014- Dec 2015​ ​​


7.5       Resource Consents

The Dunsandel water supply has a number of resource consents. Table 7‑3 shows the water take permitted by the resource consents for this scheme.

Table 7Resource Consents

Consent​

Description Location Date Issued Expiry Date Consented Max Instantaneous Flow (L/s) Consented Max Daily Volume (m3/day)

CRC010891.1

To take and use groundwatercnr Sh1 & Hororata Dundanel Roads And Cnr Tramway And, IRVINES ROADS DUNSANDEL12-Feb-1031-Jan-3522.51944

 

7.6       Water Quality

The Dunsandel water supply is a non-secure source and is currently sampled twice weekly at the source, treatment plant and weekly in the reticulation.

The following details the E. coli transgressions for the period 2012 to 2020.

Source

There have been 50 incidences of E. coli identified in source water during this period, highlighting the importance of water treatment for this scheme.

Figure 73 E. coli Transgressions - Source


Treatment

There has been one E. coli treatment transgression during this period which occurred in October 2014.

Zone

There has been one E. coli transgressions during this period which occurred in January 2013.​

​Chemical Analysis

The following is a summary of the raw water chemical analysis carried out at the Dunsandel Water Supply. 

Table 74  Dunsandel Water Supply Raw Water Chemical Analysis Summary

Parameter Standards
2008
​2011
​2013
2015 2017 ​2018
​2019
Status
Total Lead (g/m3)0.01 (Maximum Acceptable Value)
​<0.0001
​<0.00011
​0.00013
0.0002

< 0.00011​<0.00011
​<0.00011

pH (pH units)7-8.5 (Guideline Value)
​7.1
​7.1
​7.3
7.47.2​7.3
​7.3
Total Hardness (g/m3 as CaCO3)<200 (Guideline Value)
​63
​54
​54
6763.2
​74.3
​79.7

Total Calcium (g/m3)n/v​16
​13.7
​13.9
16.8
16.64
​19.71
​21.02
Total Iron  (g/m3)<0.2 (Guideline Value)
​<0.02
​<0.021
​<0.021
<0.021< 0.021​<0.021
​<0.021

Total Sodium (g/m3)<200 (Guideline Value)
​9.4
​8.8
​8.6
109.86​11.01
​11.94
Nitrate - Nitrogen (g/m3)11.3 (Maximum Acceptable Value)
​4.2
​2.8
​2.7
3.64.5​6.54
​6.54


7.7       Scheme Assets

A summary of material and diameter for pipes in Dunsandel is shown by Figure 7‑4 and Figure 7‑5.

Figure 74 Pipe Material – Dunsandel


Figure 75 Pipe Diameter – Dunsandel

 

7.8       Operational Management

The water supply is operated and maintained under two maintenance contracts as follows:

  • Contract 1241: Water Services Contract.  Contract is with SICON who undertakes investigations, conditions inspections, proactive and reactive maintenance and minor asset renewals; and
  • Contract 1202: Parks and Reserves Contract.  Contract is with SICON who undertakes the maintenance of land scape features related to water services e.g. mowing, gardens etc.

Water quality sampling is completed under an agreement with Food and Health Ltd as required.

 

7.9       Photos of Main Assets

Dunsandel - Photo 1 Site Layout.png

Photo 1: Site Layout

7.10       Risk Assessment

A risk assessment has been undertaken for the Dunsandel scheme. The key output from the risk assessment is the identification of any extreme and high risks which need to be mitigated. In order to mitigate these risks they have been included and budgeted for in the projects within this LTP. 

Table 7‑5 outlines the risk priority rating, Table 7‑6 outlines the risks and the list of key projects is found in Table 7‑10. The list of district wide risks can be found in 5Waters Activity Management Plan: Volume 1.

Table 75 Risk Priority Rating

Risk Score Level of Risk Risk Response
> 50Extreme

Awareness of the event to be reported to Council. 

Urgent action to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

35-50Very HighRisk to be eliminated / mitigated / managed through normal business planning processes with responsibility assigned.
14-35HighManage risk using routine procedures.
3.5-14ModerateMonitor the risk.
< 3.5Low

Awareness of the event to be reported to Council. 

Immediate action required to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.


Table 76 Risks – Dunsandel

Risk​ Action / Project​​ Year Identified 2014 Risk Rating 2017 Risk Ratinh ​Residual Risk Rating
Lack of water storageDemolish the concrete tank and replace with 33m3 tanks (min 4)2014272712
Often power outages (especially when wind storms occur)Install a generator on this scheme2014122.12.1
Only one source of supply - risk of lossInvestigate suitable location for second bore2014666
Electrical failure due to lightning or network spikesInstall surge diverters2014103.53.5
Failure to meet NES water meter standardsNES Water Meter Compliance20142066
Inability to collect income from non-metered propertiesInstall property water meters2014270.60.6
Non-compliance with the DWSNZ​
DWSNZ - Age Testing2014100.70.7

​Non-consented activities

Renewal of consents

​2014
27
​27
6
Inadequate treatment under all conditions ​Install filtration2017

 40
​7


7.11       Asset Valuation Details

The total replacement value of assets within the Dunsandel water scheme is $1,906,636 with further details in Table 7‑7 below.

Table 77 Replacement Value, Dunsandel

​Asset Class 1​
Asset Class 2​Sum of Replacement Value
Plant and Equipment ​
$596,693​
​​Water Reticulation ​​ ​​ ​​

Hydrant
$59,003​
Lateral$39,417
Pipe
$1,040,827
Supply Point$136,576
Valve$30,256

 ​

7.12       Renewals

The renewal profile has been taken from the 2019 5 Waters Valuation. A graph showing the renewals for this scheme are shown by Figure 7‑6 below. The majority of renewals occur in 2022/2023.

Figure 7‑6 Dunsandel Water Renewal Profile

 

7.13       Critical Assets

The criticality model for Dunsandel has been updated for the 2021 AcMP. The methodology of the criticality model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the criticality has been calculated for the reticulation assets. Table 7‑8 and Figure 7‑7 below shows the calculated criticality for all of the assets within this scheme that have a recorded known length.

Table 78 Length of Assets per Criticality Level

Criticality Bands
Length (m)
5
Low2,559
4
Medium-Low3,039
3
Medium2,127
2
Medium-High1,088​
1​
High0


​​​
​​ Figure 7-7
DUNSANDEL Water - Criticality

Open larger map: 'Water Criticality'

​​​

​​7.14       Asset Condition

The asset condition model was run for Dunsandel in 2021. The methodology of the model can be found in 5Waters Activity Management Plan: Volume 1 which provides details of how the model has been calculated for the pipe reticulation assets. Figure 7‑8 below shows the level of asset condition for these assets within this scheme that have a recorded known condition.

​​​
​​ Figure 7-8
DUNSANDEL Water - Condition

Open larger map: 'Water Condition'

​Table 7‑9 provides a description of the condition rating used within the condition model.

Table 79 Asset Condition Grading

Condition Rating​ Grading
1.0Excellent
2.0Good
3.0Moderate
4.0Poor
5.0+Fail

 

The number of pipe faults is also measured through the asset management system. Figure 7‑9​ shows the known historic pipe failures within this scheme.

​​​
​​ Figure 7-9
DUNSANDEL Water - Scheme map

Open larger map: 'Water Scheme'

​​

7.15       Funding Program

The 10 year budgets are shown by Table 3‑12. Bu​dgets are split into expenditure, renewals, projects and capital projects. Expenditure and renewals have been reported on a district-wide basis in Volume 1. 

All figures are ($) not adjusted for CPI “inflation".  They are calculated on historical data, and population growth where relevant.​

Table 7-10 Budget Summary

Years Projects Capital Projects
2021/2022 $31,000
 $15,000
2022/2023
 -
 $590,000
2023/2024 -
 $400,000
2024/2025 -
 -
2025/2026 -
 -
2026/2027 -
 -
2027/2028 -

2028/2029
 -
 -
2029/2030
 -
 -
2031/2032
 -
 $600,000
Total  $31,000
 $1,605,000

An explanation of the categories within the budgets are as follows below:

  • Expenditure consists of operation and maintenance costs;
  • Renewals are replacement of assets which are nearing or exceeded their useful life;
  • Projects are investigations, decisions and planning activities which exclude capital works; and
  • Capital projects are activities involving physical works.

Table 7-11 Key Projects

Account Label GL Description​  Year 1($)  Year 2($)  Year 3($) Years 4 to 10 Funding Split *
​Capital Projects​
-
WTP Upgrade
 -
$560,000
$400,000
-
TBC
​Capital Projects
​-
​Second WTP/source/reservoir
​-
​-
-
​$600,000
​TBC

​Capital Projects
-
Valves each side of SH
​-
$30,000
​-
​-
100% LoS​

​Capital Projects
​-
​Pressure sensors
​$15,000

100% LoS

 * Where LoS refers to Level of Service and G refers to Growth

The list of district wide projects can be found in 5Waters Activity Management Plan: Volume 1.

Discussion on Projects

Projects​​​ have been determined based on their:

  • Relevance to the scheme
  • Requirement to be completed under legislatio​n
  • Ability to bring the scheme up to or maintain the Level of Service required under council's Asset Management Policy. 

Many projects are jointly funded by more than one scheme and activity.  Each scheme pays a pro-rata share only, equivalent to the number of connections.

Discussion on Capital and Proj​ects

Where relevant, Capital (Levels of Service) and Capital (Growth) projects have been included in the scheme financial details. 

Levels of Service Projects and growth splits have been provided to ensure the costs of population driven works are clear.​​​​​


<< ​​5-Waters Volume 2 - Water Supplies
​​​​​​​​​​​​​​​​​​<< ​​Darfield Water Supply​​​​​
Greater West Melton Water Supply​​​​​​​ >>​​​