​​​​​​​​<< ​​5-Waters-Volume-3-Wastewater
​​​​​​​​​​​​​​​​​​<< ​​Prebbleton Wastewater Scheme​​​
Septage Disposal Facilities​ >>​​​

​​​​​​12   Rolleston Wastewater Scheme


12.1       Scheme Summary

 

Description
Quantity
Estimated Population Served ​
21,875

Scheme Coverage

(1 Jan 2021)

​​ ​
Full Charges6,338
Half Charges1,120
>1 Charges
80
System  Components ​​ ​​ ​​ ​
Piped (m)
260,410
Manholes (No.)2,364
Pump Stations (No.)13
TreatmentN/A (to Pines WWTP)
DisposalN/A (to Pines WWTP)
HistoryOriginal scheme installation date1996
Value ($) ​
Replacement Cost$88,879,203
Depreciated Replacement Cost$79,467,080
FinancialOperator cost (scheduled and reactive maintenance) per connection
$45.54/connection
Demand ​​ ​​ ​​ ​
(1 Jan - 31 Dec 2020)
Annually (m3) 1,513,542
Average daily (m3) 4,135
Peak daily (m3) 6,764
Minimum daily (m3) -
Infiltration Yes
SustainabilityUltimate discharge pointTo Pines WWTP

 

12.2       Key Issues

The following key issues are associated with the Rolleston Wastewater Scheme.  A list of district wide issues are located in 5Waters Activity Management Plan: Volume 1.

Table 121 Rolleston Scheme Issues

What's the Problem​ What we plan to do
Meeting growth requirements Complete capital upgrade program to meet growth demand.

 

12.3       Overview & History

For Rolleston, the community was initially developed with onsite treatment and disposal of wastewater via septic tanks.  Developers identified the potential for the growth in the town with availability of land for subdivision and proximity to major service routes to Christchurch, and to the west coast.

The town's original wastewater treatment plant (WWTP), known as the Rolleston (Helpet) WWTP was built by private developers (Helpet Investments Ltd) and commissioned in 1996, with a design population capacity of 4,400 population equivalents - the forecasted town population at that time.  Testing of Helpet WWTP revealed the disposal area had a reduced capacity due to soil types and the treatment plant could only manage 3900 population equivalents, utilising grass cut and carry.

Following approval in 2003 to further expand the town to 14,000 population equivalents, additional wastewater treatment and disposal capacity was required.  Resource consents for a new WWTP within the Selwyn Plantation (hence the name of 'Pines' I WWTP), some 5 km from the town were granted in December 2003.  The plant was constructed in 2006 and commissioned in 2007 to provide an additional capacity of 6,000 population equivalents. 

All Rolleston wastewater is now treated and disposed of at the Pines Treatment Plant, see Section 5.0 for more details about the treatment plant.

The Helpet WWTP has now been decommissioned from service and being upgraded to provide flow buffer storage.  The Helpet pump station was diverted in early 2015 to the west of the site to connect to the new Selwyn Road pump station.  A contamination report was commissioned for the site and confirm that the site was appropriate for development.

The IZone industrial park is connected to the Rolleston wastewater network, with the largest customer being Westland Dairy.  Ongoing expansion of Westland Dairy and the IZone development will utilise spare capacity in the wastewater network.

​​​
​​ Figure 12-1
ROLLESTON Sewer - Scheme map

Open larger map: 'Sewer Scheme'

V3 Rolleston - Scheme Schematic 1.png

V3 Rolleston - Scheme Schematic 2.png

Figure 122 Scheme Schematics x2


V3 Rolleston - Master Plan.png

Figure 123 Rolleston Master Plan


 V3 Rolleston - Pump Station Failure Map.jpg

Figure 124 Pump Station Failure Map


12.4       System Capacity

In recent years there has been rapid residential growth in the Rolleston and West Melton communities. This has placed a strain on the existing wastewater collection system. Therefore, with the implementation of the ESSS, the wastewater system has been expanded in stages to meet the increasing flows. A wastewater masterplan has been established to structure the expansion of scheme to meet the timing of new development.  The capacity of existing catchment pump stations, while not yet reached, will need to be monitored and upgraded as pump renewals are considered. Figure 12‑5 below shows the predicted population growth for Rolleston.

V3 Rolleston & West Melton - Projected PE Growth.png

Figure 125 Projected PE Growth - Rolleston & West Melton


V3 Rolleston - Wet Weather Flow Capacity Map.jpg
Figure 126 Wet Weather Flow Capacity Map

​ 

12.5       Resource Consents

Rolleston township is part of the ESSS scheme. Therefore, all wastewater is pumped to the Pines Treatment Plant. The resource consents required for this treatment plant are in the ESSS section of this plan. Consents for the old treatment plant are still active, however the majority of this site is no longer operational.  The consents for the Helpet plant are shown below in Table 12​‑2.

Table 122 Resource Consents

Consent​

Description Location Date Issued Expiry Date Quantities

CRC950311.1



To discharge contaminants (including odours and aerosols) into the air from spray and trickle irrigation of treated domestic sewage effluent onto 13.8 hectares of land, from the storage of sewage screens and sludge from an extended aeration sewage treatment plant located between Springston Rolleston and Lincoln Rolleston Roads, at or about map reference M36:614-337.BTWN Springston-Rolleston & Springston-Lincoln Roads, ROLLESTON12-Dec-0031-Mar-30 N/A

CRC950310.2



To discharge contaminants to landBTWN Springston-Rolleston & Springston-Lincoln Roads, ROLLESTON17-Mar-0531-Mar-30110

 

12.6       Scheme Assets

A summary of the assets within this scheme is outlined in this section.


12.6.1   Reticulation Overview

A summary of material and diameter for pipes is shown in Figure 12‑7 and Figure 12‑8.

Figure 127 Pipe Material - Rolleston


Figure 128 Pipe Diameter – Rolleston

 

12.6.2   Treatment and Disposal

Further reference to the treatment and disposal of Rolleston wastewater is described in Section 5.0.


12.6.3   Design

The wastewater collection system has been designed in accordance with the appropriate New Zealand engineering design guidelines at the time of construction and in accordance with the Selwyn District Council Engineering Design Standards. Specific designs for portions of the scheme outside of these standards have been considered where detailed engineering designs have been provided.


12.6.4   Pump Stations

There are a total of seven pump stations with the details outlined in Table 12‑3 below.

Pump stations where the standby / assist pump is predicted to start have been highlighted in y​ellow and red for those that experience a peak wet weather response.

Yellow   Pumps are can convey the peak flow without backing up the system

Red        Pumps are unable to convey the peak flow causing the system to back up

Table 123 Pump Station Overview

Site Name​ Wet well dimensions No of pumps Pump curve used Recorded instantaneous pump rate (L/s) Model Pump Rate (L/s) ADWF (L/s) PDWF (L/s) PWWF 1 in 5 year ARI (L/s)
Rolleston (S) Boulez Mews PS1800Ø2Flygt 3068 170 HT2162.53.00.10.30.3
Rolleston (S) George Holmes Dr PS3050Ø2Flygt 3202 180 MT43170648.48.98.9
Rolleston (S) Goldrush Ln PS1800Ø2Flygt 3085 183 HT48120170.61.61.6
Rolleston (S) Goulds Rd PS2400Ø2Flygt 3127 180 HT48115184.113.613.6
Rolleston (S) Helpet PS3000 x 25002Flygt 3202 180 HT450110-140105-13518.151.150.8
Rolleston (S) Marlowe Pl PS1800Ø2Flygt 3085 183 MT46188.40.20.50.5
Rolleston (S) Runners Rd PS2600Ø2Flygt 3102 181 MT46116
171.02.02.0

 

Table 124 Pump Station Storage Time Analysis

Pump Station   Hours until HLA reached Hours until first spill Spill Loca​tion - AMS ID
Rolleston (S) Boulez Mews PSSubdivision47.950.7551108
Rolleston (S) George Holmes Dr PSService industrial area - has capacity to service Izone industrial area6.98.1551007
Rolleston (S) Goldrush Ln PSLift station to reticulation flowing to HelpetNANANA
Rolleston (S) Goulds Rd PSLift station to reticulation flowing to Helpet4.56.8550248
Rolleston (S) Helpet PSLift sewage up to new gravity line to Selwyn Road Pump station12.315.1550166
Rolleston (S) Marlowe Pl PSSubdivision27.330.0551137
Rolleston (S) Runners Rd PSServices the Department of Corrections and CYFS73.574.7542308


12.6.5   Helpet Emergency Storage

Since the completion of the upgrade to the Pines WWTP in 2012, the Helpet WWTP is now no longer in service as a treatment facility. The existing site was repurposed as an emergency wastewater storage facility. Figure 12‑9 shows the path of the wastewater within the facility.

V3 Rolleston - Flow Diagram showing path of the wastewater.png

Figure 129 Flow Diagram showing path of the wastewater

Under normal operation, wastewater from the upstream catchment enter the site via the flow splitter chamber. Flow is then diverted into the Helpet Pump Station (PS) wet well through a DN375 pipe. The wastewater is then pumped to the Farrington gravity trunk main. Under normal operations, the storage facilities will not be used.

In the event the pumps are unable to match the incoming flow or a mechanical/electrical failure of the Helpet pump station occurs, the water level will rise in the wet well and the flow splitter chamber. If the level rises high enough, it will begin to spill over a fixed weir to the Helpet inlet chamber / pump station and then to the primary storage tanks (previously operating as anoxic tanks under their previous WWTP function).

The tanks will fill sequentially. As each tank reaches its top water level, a steel box weir will convey flows to begin to fill the next tank. Sequential filling minimises the effort required to wash down the tanks after an event. Once the primary tanks are full, flows are then conveyed via a terminal weir to the secondary storage tanks (previously operating as Oxidation tanks under their previous WWTP function). The final chamber within the storage system is the tertiary chamber (previously operating as the sludge storage tank under their previous WWTP function).

A separate circuit of DN150 pipes returns flow back to the pump station. “WaStop" sock type check valves in the return circuit ensure the tanks cannot fill via these pipes. Table 12‑5  shows the volume and spill level (slightly below the top water level) of each of the tanks.

Table 125 Summary of the volume and assumed safe top weir level of the storage facilities

Existing Tank​ Approximate Volume (m3) Assumed Safe Top Water Level (m)
Old Inlet PS11.245.67
Tank 163.545.63
Tank 261.945.62
Tank 360.245.58
Tank 458.5645.55
Ditch 1 (Sth)218.945.51
Ditch 2 (Sth)209.245.48
Sludge tank17.845.45

 

12.6.6   Rising Mains

Table 12‑6 Rising Main Overview

Pump Sta​tion Town Total Length (m) Total Volume (m3) ADWF (L/s) Uphill Retention Time (hours) Drain Time (hours) Total Time (hours) Model Max Pressure (kPa) SCADA Max Pressure (kPa)
Rolleston (S) Boulez Mews PS Rolleston940.20.10.50.00.5110No data​
​Rolleston (S) George Holmes Dr PS​​
Rolleston2,501158.18.45.20.05.2315No data
Rolleston (S) Goldrush Ln PSRolleston230.20.60.10.00.120No data
Rolleston (S) Goulds Rd PSRolleston5248.34.1
0.60.00.6105No data
Rolleston (S) Helpet PSRolleston94227.618.10.21.11.329595 – 180**
Rolleston (S) Marlowe Pl PSRolleston1601.40.22.10.02.130No data
​Rolleston (S) Runners Rd PSRolleston4757.91.02.30.02.340No data

 

12.7       Operational Management

The wastewater schemes are operated and maintained under the maintenance contract as follows:

  • ​Contract 1241: Water Services Contract. Contract is with SICON who undertakes investigations, conditions inspections, proactive and reactive maintenance and minor asset renewals.

Wastewater sampling is completed under an agreement with Food and Health Ltd as required.

 

12.8       Photos of Main Assets


V3 Rolleston - Photo 1 - Helpet Pump Station.jpg
Photo 1 Helpet Pump Station
V3 Rolleston - Photo 2 - Burnham School Road Pump Station.jpg
 Photo 2 - Burnham School Road Pump Station


12.9       Risk Assessment

A risk assessment has been undertaken for the Rolleston scheme. The key output from the risk assessment is the identification of any extreme and high risks which need to be mitigated. In order to mitigate these risks they have been included and budgeted for in the projects within this LTP. Table 12‑7 details the risk priority rating, Table 12‑8 outlines the risks and the list of key projects is found in Table 12‑13.

Table 127 Risk Priority Rating

Risk Score Level of Risk Risk Response
> 50Extreme

Awareness of the event to be reported to Council. 

Urgent action to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

35-50Very HighRisk to be eliminated / mitigated / managed through normal business planning processes with responsibility assigned.
14-35HighManage risk using routine procedures.
3.5-14ModerateMonitor the risk.
< 3.5Low

Awareness of the event to be reported to Council. 

Immediate action required to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

 

Table 128 Risks - Rolleston

Risk​ Action/Project Year Identified 2014 Risk Rating 2017 Risk Rating Residual Risk Rating
Increased loading from development overloads pump stationUpgrade pumps (one) in Goulds Road2014454520


The list of district wide risks can be found in 5Waters Activity Management Plan: Volume 1.

 

12.10       Asset Valuation Details

The total replacement value of assets within the Rolleston Scheme is $88,879,203 as detailed in Table 12‑9 below. ​

Table 129 Replacement Value, Rolleston

Asset Class 1 Asset Class 2 Sum of Replacement Value
Plant and Equipment ​
$2,456,113
​Wastewater Reticulation
Chamber$320,073
Lateral$25,300,018
Manhole$13,453,794
Pipe$47,193,096
Valve$153,843


12.11       Renewals

The renewal profile has been taken from the 2019 5 Waters Valuation. A graph showing the renewals for this scheme are shown by Figure 12‑10 below.

Figure 1210 Rolleston Wastewater Renewal Profile

 

12.12       Critical Assets

The criticality model for Rolleston has been updated for the 2021 AcMP. The methodology of the criticality model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the criticality has been calculated for the reticulation assets. Table 12‑10 and Figure 12‑11 below shows the calculated criticality for all of the assets within this scheme that have a recorded known length.

Table 1210 Length of Assets per Criticality Level

Criticality Bands Length (m)
5
Low198,625
4
Medium-Low17,947
3
Medium16,267
2
Medium-High13,916
1
High
5,101​


​​​
​​ Figure 12-11
ROLLESTON Sewer - Criticality map

Open larger map: 'Sewer Criticality'


12.13       Asset Condition

The asset condition model was run for Rolleston in 2021. The methodology of the model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the model has been calculated for the reticulation assets (particularly pipes). Figure 12‑12 below shows the level of asset condition for all of the assets within this scheme that have a recorded known condition.​

​​​
​​ Figure 12-12
ROLLESTON Sewer - Condition map

Open larger map: 'Sewer Condition'

Table 12‑11 provides a description of the condition rating used within the condition model.

Table 1211 Asset Condition Grading

Condition Rating​ Grading
1.0Excellent
2.0Good
3.0Moderate
4.0Poor
5.0+Fail

 

12.14       Funding Program

The 10 year budgets for Rolleston are shown by Table 12‑12. Budgets are split into expenditure, renewals, projects and capital projects. Expenditure and renewals have been reported on a district-wide basis in Volume 1.

All figures are ($) not adjusted for CPI “inflation".  They are calculated on historical data, and population growth where relevant.

Table 1212 Rolleston Budget Summary

Years Projects Capital Projects
2021/2022 $11,000
$120,000
2022/2023 -
$250,000
2023/2024 -
-
2024/2025 -
$500,000
2025/2026 -
-
2026/2027 -
-
2027/2028 -
-
​2028/2029
​-
​-
​2029/2030
​-
​-
​2030/2031
​-
​-
Total$11,000
$870,000

 

An explanation of the categories within the budgets are as follows below:

  • Expenditure consists of operation and maintenance costs;
  • Renewals are replacement of assets which are nearing or exceeded their useful life;
  • Projects are investigations, decisions and planning activities which exclude capital works; and
  • Capital projects are activities involving physical works.

​Table 1213 Key Projects

Account Label GL Description  Year 1 ($)  Year 2 ($)  Year 3 ($) Years 4 to 10 Funding Split *
Capital Projects-
Pump station upgrade to meet high-volume flows
-
$250,000
-
-
TBC
​Capital Projects
​-
​Upgrade odour management system at Selwyn Rd PS
​$120,000
​-
​-
​-
​TBC
Projects &
Capital Projects
​-
​Cover wastewater overflow storage tanks
​$10,000
​-
​$15,000
​$500,000
​TBC

* LoS refers to Level of Service; G refers to Growth​

The list of district wide projects can be found in 5Waters Activity Management Plan: Volume 1.

Discussion on Projects

Projects have been determined based on their:

  • Relevance to the scheme
  • Requirement to be completed under legislation
  • Ability to bring the scheme up to or maintain the Level of Service required under council's Asset Management Policy. 

Many projects are jointly funded by more than one scheme and activity.  Each scheme pays a pro-rata share only, equivalent to the number of connections.

Discussion on Capital and Projects

Where relevant, Capital (Levels of Service) and Capital (Growth) projects have been included in the scheme financial details. 

Levels of Service Projects and growth splits have been provided to ensure the costs of population driven works are clear.

​​​​​​​​​​​​​​​​​​
<< ​​5-Waters-Volume-3-Wastewater
​​​​​​​​​​​​​​​​​​<< ​​Prebbleton Wastewater Scheme​​​
Septage Disposal Facilities​ >>​​​