​​​​​​​​​​​​<< ​​5-Waters-Volume-3-Wastewater
​​​​​​​​​​​​​​​​​​<< ​​Castle Hill Wastewater Scheme​​​
​3   Claremont Wastewater Scheme


3.1       Scheme Summary


Description​ Quantity
Estimated Population Served ​172

Scheme Coverage

(1 Jan 2021)

​​ ​
Full Charges49
Half Charges5
>1 Charges5
System  Components ​​ ​​ ​​ ​
Piped (m)3,040
Manholes (No.)16
Pump Stations (No.)1
TreatmentPackage treatment plant
DisposalSubsurface disposal fields
HistoryOriginal scheme installation date2005
Value ($) ​
Replacement Cost$2,566,534
Depreciated Replacement Cost$1,891,300
Financial
Operator cost (scheduled and reactive maintenance) per connection​

$1,002.58/connection

Demand ​​ ​​ ​​ ​​
(1 Jan - 31 Dec 2020)
Annually (m3)10,748
Average daily (m3)29.4
Peak daily (m3)157.0
Minimum daily (m3)-
Infiltration Not a significant issue for this scheme
SustainabilityUltimate discharge pointStorage and subsurface disposal (irrigation)

 

3.2   Key Issues

The following key issues are associated with the Claremont Wastewater Scheme.  A list of district wide issues are located in 5Waters Activity Management Plan: Volume 1.

Table 3‑1 Claremont Scheme Issues

What's the Problem​ What we plan to do
Cost of  scheme operation and maintenance Council will review options to reduce operation and maintenance costs and optimise renewals.

 

3.3       Overview & History

Claremont is an independently serviced subdivision adjacent to Templeton.  Wastewater is treated by a small 'package' treatment plant and effluent is disposed of to land.  Construction was completed in 2005 and the assets adopted by Council in 2007.  There is a small rating base which is required to contribute solely to all costs associated with the lifecycle management of this scheme. 

​​​
​​ Figure 3-1
CLAREMONT Sewer - Scheme map

Open larger map: 'Sewer Scheme'


V3 Claremont - Scheme Schematic.png 

Figure 3‑2 Scheme Schematic


3.4       System Capacity

The current Claremont wastewater flows are consistent with the design flows for the current number of connected properties.  Consent conditions and system design meets correct needs but limit further growth.

There is not expected to be significant growth in the area serviced by this scheme and scheme expansion is not expected to be required over the planning horizon of this AcMP.


3.5       Resource Consents

The Claremont wastewater scheme has a number of resource consents. Table 3‑2 shows the discharge permitted by the resource consents for this scheme.

Table 3‑2 Resource Consents

Consent

 ​

Description Location Date Issued Expiry Date

Quantities

(m3/day)

CRC000095.2

To discharge domestic sewage effluent to ground via a "Blivot Aerotor" treatment system and "RAAM" irrigation disposal system, at or about map reference NZMS 260 M36:665-380.Waterholes Road, TEMPLETON20-Jun-089-Feb-3558

​There are no consents up for renewal during the term of this Plan.  There is no compliance issues associated with the Claremont Sewerage Scheme.

 

3.6       Scheme Assets

A summary of the assets within this scheme is outlined in this section.


3.6.1   Reticulation Overview

A summary of material and diameter for pipes is shown in Figure 3‑3 and Figure 3‑4.

Figure 3‑3 Pipe Material – Claremont


​Figure 3‑4 Pipe Diameter – Claremont

 

3.6.2   Treatment and Disposal

The treatment facilities consist of a Smith & Loveless MICROFAST secondary aerated package plant.

Table 3‑3 Treatment Plant Package

System​ Description Year Installed/ Upgraded
Flow SplitterFlow splitter box2005
Settling tank2x22m3 Primary settling tanks with outlet filters2005
Aeration2x32m3 MICROFAST 9.0 secondary aeration tanks with blower and aeration equipment2005
StorageFinal storage tank2005
DisposalSub surface 2005

 

3.6.3   Design

The design data for the Claremont system is tabled below.

Table 3‑4 Design Data

Per Capita Flow

L/per/day

Peak Day Flow

m3/day

Households
1745858

Claremont Wastewater Scheme is a small scheme with no allowance for expansion beyond the package plant capacity.  Expansion is not likely to be required within the foreseeable future as once the number of connection reaches the subdivision maximum so too will the design capacity have been reached.  Any further development in the vicinity will require rezoning of land and wastewater and disposal for the development would need to be assessed as part of the development.

 

3.6.4   Pump Stations

The pump station in Devine Drive pumps to the wastewater treatment plant.

 

3.7       Operational Management

The wastewater schemes are operated and maintained under the maintenance contract as follows:

  • Contract 1241: Water Services Contract.  Contract is with SICON who undertakes investigations, conditions inspections, proactive and reactive maintenance and minor asset renewals.

Wastewater sampling is completed under an agreement with Food and Health Ltd as required.

 

3.8       Photos of Main Assets


V3 Claremont - Photo 1 - Package Plant.jpg
Photo 1 - Package Plant

 

3.9       Risk Assessment

A risk assessment has been undertaken for the Claremont scheme. The key output from the risk assessment is the identification of any extreme and high risks which need to be mitigated. In order to mitigate these risks they have been included and budgeted for in the projects within this LTP. Table 3‑5 details the risk priority rating and Table 3‑6 outlines the risks for this scheme.

Table 3‑5 Risk Priority Rating

Risk Score​ Level of Risk Risk Response
> 50Extreme

Awareness of the event to be reported to Council. 

Urgent action to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

35-50Very HighRisk to be eliminated / mitigated / managed through normal business planning processes with responsibility assigned.
14-35HighManage risk using routine procedures.
3.5-14ModerateMonitor the risk.
< 3.5Low

Awareness of the event to be reported to Council. 

Immediate action required to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

 

Table 3‑6 Risks - Claremont

Risk​ Action/Project Year Identified 2014 Risk Rating 2017 Risk Rating Residual Risk Rating
System is not optimised resulting in increased operational costs Replace manual valves with solenoid valves and control via Datran2014121212
Failure of power supply to schemeOpen up 5th irrigation zone to provide operational redundancy 2014121212
Non-consented activitiesRenewal of consents201427276
Limited capacity and redundancy Extend irrigate to 5th area2017 20.7

The list of district wide risks can be found in 5Waters Activity Management Plan: Volume 1.

 

3.10       Asset Valuation Details

The total replacement value of assets within the Claremont Scheme is $2,587,966 as detailed in Table 3‑7.

​Table 3‑7 Replacement Value, Claremont

Asset Class 1​ Asset Class 2 Sum of Replacement Value
Plant and Equipment ​
$1,492,128
Wastewater Reticulation ​​ ​​ ​​ ​
Chamber$7,392
Lateral$209,250
Manhole$139,176
Pipe$737,916
Valve$2,103


​3.11       Renewals

The renewal profile has been taken from the 2019 5 Waters Valuation. A graph showing the renewals for this scheme are shown by Figure 3‑5 below.

Figure 3‑5 Claremont Wastewater Renewal Profile


3.12       Critical Assets

The criticality model for Claremont has been updated for the 2021 AcMP. The methodology of the criticality model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the criticality has been calculated for the reticulation assets. Table 3‑8 and Figure 3‑6 below show the calculated criticality for all of the assets within this scheme that have a recorded known length.

Table 3‑8 Length of Assets per Criticality Level

Criticality Bands​ Length (m)
5
Low3,453​
4
Medium-Low0
3
Medium0
2
Medium-High0
1
High0


​​​
​​ Figure 3-6
CLAREMONT Sewer - Criticality map

Open larger map: 'Sewer Criticality'

​​

3.13       Asset Condition

The asset condition model was run for Claremont in 2021. The methodology of the model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the model has been calculated for the reticulation assets (particularly pipes). Figure 3‑7 below shows the level of asset condition for all of the assets within this scheme that have a recorded known condition.

​​​
​​ Figure 3-7
CLAREMONT Sewer - Condition map

Open larger map: 'Sewer Condition'

Table 3‑9 provides a description of the condition rating used within the condition model.

Table 3‑9 Asset Condition Grading

Condition Rating​ Grading
1.0Excellent
2.0Good
3.0Moderate
4.0Poor
5.0+Fail

 

3.14       Funding Program

The 10 year budgets for Claremont are shown Table 3‑10. Budgets are split into expenditure, renewals, projects and capital projects. Expenditure and renewals have been reported on a district-wide basis in Volume 1. 

All figures are ($) not adjusted for CPI “inflation".  They are calculated on historical data, and population growth where relevant.

Table 3‑10 Claremont Budget Summary

Years​ Projects Capital Projects
2021/2022 -
 -
2022/2023$30,000
 -
2023/2024$100,000
 -
2024/2025 -
$500,000
2025/2026 -
 -
2026/2027 -
 -
2027/2028
 -
 -
​2028/2029
​-
​-
​2029/2030
​-
​-
​2030/2031
​-
​-
Total $130,000
$500,000


An explanation of the categories within the budgets are as follows below:

  • Expenditure consists of operation and maintenance costs;
  • Renewals are replacement of assets which are nearing or exceeded their useful life;
  • Projects are investigations, decisions and planning activities which exclude capital works; and
  • Capital projects are activities involving physical works.

Table 3‑11 Key Projects

Account​ Label​ GL Description  Year 1 ($)  Year 2 ($)  Year 3 ($)  Years 4 to 10 Funding Split *
Capital Projects-
Site upgrades/pre-treatment
-
$30,000
$100,000
$500,000
100% LoS

LoS refers to Level of​ Service

The list of district wide projects can be found in 5Waters Activity Management Plan: Volume 1.

Discussion on Projects

Projects have been determined based on their:

  • Relevance to the scheme
  • Requirement to be completed under legislation
  • Ability to bring the scheme up to or maintain the Level of Service required under council's Asset Management Policy. 

Many projects are jointly funded by more than one scheme and activity.  Each scheme pays a pro-rata share only, equivalent to the number of connections.

Discussion on Capital and Projects

Where relevant, Capital (Levels of Service) and Capital (Growth) projects have been included in the scheme financial details. 

Levels of Service Projects and growth splits have been provided to ensure the costs of population driven works are clear.


​<< ​​5-Waters-Volume-3-Wastewater
​​​​​​​​​​​​​​​​​​<< ​​Castle Hill Wastewater Scheme​​​
Darfield and Kirwee Wastewater Scheme​​​ >>​​​