​​​​​​​​​​​​​​​<< ​​5-Waters-Volume-3-Wastewater ​​​1   Arthurs Pass Wastewater Scheme


1.1       Scheme Summary


Description​​ Quantity
Estimated Population Served ​
29

Scheme Coverage

(1 Jan 2021)​

​​ ​
Full Charges
9
Half Charges1
>1 Charges0
System  Components​
Piped (m)430
Manholes (No.)7
Pump Stations (No.)0
TreatmentPrimary and Secondary Septic Tank
DisposalSand beds
HistoryOriginal scheme installation date1999
Value ($) ​
Replacement Cost$304,471
Depreciated Replacement Cost$193,875
Financial
Operator cost (scheduled and reactive maintenance) per connection​

$6,023.64/connection

Demand 
(1 Jan - 31 Dec 2020)
Annually (m3)5,310
Average daily (m3)14.5
Peak daily (m3) 2,561
Minimum daily (m3)0.0
Infiltration-
SustainabilityUltimate discharge pointDischarge to ground within a national park

 

1.2       Key Issues

The following key issues are associated with the Arthurs Pass Wastewater Scheme.  A list of district wide issues are located in 5Waters Activity Management Plan: Volume 1.

Table 1‑1 Arthurs Pass Scheme Issues

What's the Problem​ What we plan to do
Cost of  scheme operation and maintenance

Council will review options to reduce operation and maintenance costs and optimise renewals.

In September 2015, the facility was inspected.  It was found that the Rough Creek STP appears to be performing well, and is consistent with the expectations outlined in the design of the system.

 

1.3       Overview & History

The sewer network serves the southern side of Sunshine Terrace (originally known as Rough Creek Subdivision).  The sewage gravitates to a large septic tank and sand soakage disposal area.  The majority of properties in the village have on-site septic tanks. 

The remote location and harsh alpine environment present challenges for operation and maintenance of a wastewater scheme.  The village can be isolated following heavy snowfall and storm events that periodically close State Highway 73.

The community is located within the alpine fault line, and is expected to incur significant damage to its water infrastructure should a significant event occur.

​​​
​​ Figure 1-1
ARTHURS PASS Sewer - Scheme map

Open larger map: 'Sewer Scheme'


V3 Arthurs Pass - Funding Summary - Scheme Schematic.png

Figure 1‑2 Scheme Schematic


1.4       System Capacity

In general the Arthurs Pass scheme is underutilised as the occupancy rate within the houses that the scheme serves is low.  There are peak periods but these too are well within the consented limits.  During freezing conditions people tend to run their taps resulting in peak flows, but these are isolated cases. Refer to Section 1.6.3 for the design capacity of the system.

There is not expected to be significant growth in the area serviced by this scheme and scheme expansion is not expected to be required over the planning horizon of this AcMP.

 

1.5       Resource Consents

The Arthurs Pass wastewater scheme has a number of resource consents. Table 1‑2 shows the discharge permitted by the resource consents under Selwyn District Councils name in Arthurs Pass.

Table 1‑2 Resource Consents

Consent​

Description Location Date Issued Expiry Date Quantities (m3/day)

CRC073351

To discharge contaminants to landSunshine Terrace Road, ARTHURS PASS5-Nov-0730-Oct-27
23

 

1.6       Scheme Assets

A summary of the assets within this scheme is outlined in this section.


1.6.1   Reticulation Overview

A summary of material and diameter for pipes is shown in Figure 1‑3 and Figure 1‑4.

Figure 1‑3 Pipe Material – Arthurs Pass


Figure 1‑4 Pipe Diameter – Arthurs Pass

 

1.6.2   Treatment and Disposal

Treatment and disposal consists of primary and secondary septic tanks which enables settlement of solids.  Partially treated effluent is then discharged to a sand soakage bed.  There are no known issues with the Arthur's Pass treatment and disposal facilities.  Details are tabled below.

Table 1‑3 Treatment and Disposal

Treatment & Disposal​ Description Year Installed
Primary Septic Tank23.6m3 elliptical tank with dia. 3.8 x 3.1 and height 2.9m1999
Secondary septic tank
15.9m3 elliptical concrete tank dia. 3.8 x 3.1 and height 1.9m, with two Zabel filters1999
Pump chamber in secondary chamberTwo submersible pumps (1 duty and 1 standby)1999
Sand Soakage bed
23m x 10m x 800mm deep, also contains 3 plate lysimeters for monitoring purposes1999

 ​

1.6.3   Design

The design data for the Arthur's Pass system is tabled below.

Table 1‑4 Design Data

 ​ Design Population L/c/d Design Flow m3/d

Peak Flow m3/d

Full time
222505.5

13.9

Lodge781209.36
Holiday house421807.56
Combined142  22.42

Currently the treatment plant and consent capacity is underutilised.

 

1.6.4   Pump Stations

There are no pump stations within the Arthur's Pass reticulation.  There is a pump chamber and two pumps at the secondary septic tank pumping partially treated effluent to the sand soakage bed.

 

1.7       Operational Management

The wastewater schemes are operated and maintained under the maintenance contract as follows:

  • Contract 1241: Water Services Contract.  Contract is with SICON who undertakes investigations, conditions inspections, proactive and reactive maintenance and minor asset renewals.

Wastewater sampling is completed under an agreement with Food and Health Ltd as required.

 

1.8       Photos of Main Assets

V3 Arthurs Pass - Photo 1 - Pump Station.jpg

Photo 1 - Pump Station

 

1.9       Risk Assessment

A risk assessment has been undertaken for the Arthurs Pass scheme. The key output from the risk assessment is the identification of any extreme and high risks which need to be mitigated. In order to mitigate these risks they have been included and budgeted for in the projects within this LTP. Table 1‑5 details the risk priority rating and​ Table 1‑6 outlines the risks.

Table 1‑5 Risk Priority Rating

Risk Score​ Level of Risk Risk Response
> 50Extreme

Awareness of the event to be reported to Council. 

Urgent action to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.

35-50Very HighRisk to be eliminated / mitigated / managed through normal business planning processes with responsibility assigned.
14-35HighManage risk using routine procedures.
3.5-14ModerateMonitor the risk.
< 3.5Low

Awareness of the event to be reported to Council. 

Immediate action required to eliminate / mitigate / manage the risk.

Document risk and action in the AMP.


Table 1‑6 Risks – Arthurs Pass

Risk​​​​​

Action/Project Year Identified 2014 Risk Rating 2017 Risk Rating Residual Risk Rating
Non-consented activitiesRenewal of consents201427276
Sewerage system becomes uneconomic Review operating costs and report on value engineering opportunities201412126

​​​​​​The list of district wide risks can be found in 5Waters Activity Management Plan: Volume 1.

 

1.10       Asset Valuation Details

The total replacement value of assets within the Arthurs Pass Scheme is $304,471 as detailed in Table 1‑7 below. The majority of value is made up of plant and equipment.

Table 1‑7 Replacement Value, Arthurs Pass

Asset Class 1​ Asset Class 2 Sum of Replacement Value
Plant and Equipment ​
$216,106
Wastewater Reticulation ​​ ​
Lateral$33,706
Manhole$16,797
Pipe$37,862


​1.11       Renewals

The renewal profile has been taken from the 2019 5 Waters Valuation. A graph showing the renewals for this scheme are shown by Figure 1‑5 below. ​

Figure 1‑5 Arthurs Pass Wastewater Renewal Profile

 

1.12       Critical Assets

The criticality model for Arthurs Pass has been updated for the 2021 AcMP. The methodology of the criticality model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the criticality has been calculated for the reticulation assets. Table 1‑8 and Figure 1‑6 below show​ the calculated criticality for all of the assets within this scheme that have a recorded known length.

Table 1‑8 Length of Assets per Criticality Level

Criticality Bands​ Length (m)
5
Low104
4
Medium-Low176
3
Medium0
2
Medium-High0
1
High0


​​​
​​ Figure 1-6
ARTHURS PASS Sewer - Criticality map

Open larger map: 'Sewer Criticality'


1.13       Asset Condition

The asset condition model was run for Arthurs Pass in 2021. The methodology of the model can be found in 5Waters Activity Management Plan: Volume 1 and it provides details of how the model has been calculated for the reticulation assets (particularly pipes). Figure 1‑7 below shows the level of asset condition for all of the assets within this scheme that have a recorded known condition.

​​​
​​ Figure 1-7
ARTHURS PASS Sewer - Condition map

Open larger map: 'Sewer Condition'

Table 1‑9 provides a description of the condition rating used within the condition model.

Table 1‑9 Asset Condition Grading

Condition Rating​​ Grading
1.0Excellent
2.0Good
3.0Moderate
4.0Poor
5.0+Fail

 

1.14          Funding Program

There are no projects specific to Arthurs Pass in the 10 year budgets. ​


<< ​​5-Waters-Volume-3-Wastewater